P390 Assessment Procedure ConsultationRead More
The BSC restricts the activities of Elexon and in the absence of a specific Modification any additional activities cannot be pursued by Elexon (even when those activities would be of benefit to BSC Parties, industry generally and/or the consumer).
In the past specific Modifications have been necessary which have enabled Elexon to provide the Warm Homes Discount Reconciliation service, EMR settlement, and to participate in gas performance assurance framework and REC manager appointment processes.
Such individual Modifications to extend Elexon’s vires are time consuming and can be an unnecessary distraction for industry. They can also result in Elexon being unable to pursue an opportunity within a required timeframe.
P390 seeks to introduce a framework into the BSC that allows the Elexon Board to determine whether Elexon can undertake additional activities provided certain conditions are met.
All of the conditions introduced in previous Modifications to Elexon’s vires, P330 ‘Allowing Elexon to tender for the Uniform Network Code Gas Performance Assurance Framework Administrator (PAFA) role’ and P365 ‘Enabling Elexon to tender for the Retail Energy Code (REC)’ are included, plus some additional conditions to safeguard the interests of BSC Parties.
P396 Report Phase ConsultationRead More
P396 seeks to exclude Interconnector Balancing Mechanism (BM) Units from the Main Funding Share and Supplier Volume Allocation (SVA) (Production) Funding Share Balancing and Settlement Code (BSC) Charges, in order to better facilitate the EU Third Package.
P397 Report Phase ConsultationRead More
P397 seeks to introduce a mechanism through which the Balancing and Settlement Code Company (BSCCo) determines whether Licensed Distribution System Operators (LDSOs), the National Electricicty Transmission System Operator (NETSO), certain Party Agents and BSC Agents, and BSCCo should carry out the Settlement Adjustment Processes following a demand control event (DCE). BSCCo would determine the nature of the DCE and, where necessary, determine and compare the costs and value of the DCE in order to determine whether the value of carrying out the Settlement Adjustment Processes outweigh the costs.
P399 – Report Phase Consultation v2.0Read More
We are re-issuing P399 for Report Phase Consultation as new material information in relation to the solution was provided in the first Report Phase Consultation. The ESO response identified that the cost for including the ‘tendered status’ filed will now cost an additional £350k-500k. The Workgroup have decided to keep the tendered status in the solution, but in light of this material increase in cost are re-issuing P399 for consultation.
Following the introduction of P392 ‘Amending BSC Change Process for EBGL Article 18’ in June 2020, all BSC Modifications must now consider the impact on the EBGL Article 18 terms and conditions for balancing. This requires that the Workgroup is reconvened, where there have been any representations that may require the Modification Proposal to be amended. The Workgroup must then decide whether to amend, or not, the solution and where it is amended re-consult.