Glossary Term: Supplier Force Majeure
A Supplier shall not be liable to any other Party for delay or failure in performing its obligations to the extent that such delay or failure results from or is caused directly by any event or circumstance beyond the reasonable control of the Supplier. These events, often termed as “force majeure events,” can include natural disasters, extreme weather conditions, pandemics, or other significant disruptions that are beyond the supplier’s control.
A Supplier which is affected by Supplier Force Majeure shall:
- give immediate notice to BSCCo
- use all reasonable endeavours to mitigate the impact of the Supplier Force Majeure and to remedy as soon as practicable its inability to perform
- provide notice to BSCCo within one Business Day of the Supplier Force Majeure being resolved or ceasing to apply